Day 21. Set the 3 hardwood trusses 
Day 21. Set all but the last truss 
Day 22. Built end wall and set last truss 
Day 22. Trimmed Rafters-Started Purlins 
Day 22. 11 Runs of Roofing Iron 
Day 24. Finish roof 1st side, purlins & 11 runs 2nd side 
Day 25. Roof 2nd side – one sheet short! 
Day 26. Finish Roof & Ridge Cap! 
Day 26. Skylights in DR, Kit & 2 Baths 
Day 27. Security Bars in Windows 
Day 28. Window Jambs & Start Siding 
Day 28. Windows & Siding 
Day 29. Back Door & Siding 
Day 29. Scaffolding & Siding 
Day 30. Siding – High Gable End 
Day 30. Siding – Low Gable End 
Day 31. (half day) Fascia – High Gable End 
Day 32. Doors, Windows & Siding 
Day 32. Fascia too 
Day 33. Vent, Siding, & Fascia – Gable End 
Day 33. Fascia Completed 
Day 34. Set Posts for Front Porch 
Day 35. Cleanup & Organize Containers 
Day 35. Organize Containers 
Day 36. Arrival of Container #3 
Day 36. Arrival of Water Tanks & Septic Tank 
The house from the top of Campus